Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

A dam will cost $1,000,000 to build immediately and will yield benefits of $400,

ID: 1155265 • Letter: A

Question

A dam will cost $1,000,000 to build immediately and will yield benefits of $400,000 a year for the next three years. At a discount rate of 10%, which is true?

The benefits are $1,200,000, exceeding the cost, so the project should proceed.

The benefits are $1,200,000, short of the cost, so the project should be rejected.

The benefits are $994,700, short of the cost, so the project should be rejected

The benefits are $994,700, exceeding the cost, so the project should proceed.

The benefits are $1,200,000, exceeding the cost, so the project should proceed.

The benefits are $1,200,000, short of the cost, so the project should be rejected.

The benefits are $994,700, short of the cost, so the project should be rejected

The benefits are $994,700, exceeding the cost, so the project should proceed.

Explanation / Answer

The present value (PV) of benefit should be calculated first.

PV of benefit

Year

Benefit ($), B

10% factors (F) = 1 / (1 + 0.10) ^n [where n = years]

B × F

1

400,000

0.9091

363,640

2

400,000

0.8264

330,560

3

400,000

0.7513

300,520

PV

994,720

Therefore, the PV of benefits is $994,700 (rounded). This should be deducted from the initial cost top get NPV.

NPV = PV of benefits – Initial cost

            = 994,700 – 1,000,000

            = -5,300

Since the NPV is negative, the PV of benefits becomes short. Therefore, there should be a rejection.

Answer: 3rd option

Year

Benefit ($), B

10% factors (F) = 1 / (1 + 0.10) ^n [where n = years]

B × F

1

400,000

0.9091

363,640

2

400,000

0.8264

330,560

3

400,000

0.7513

300,520

PV

994,720