Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider the replacement situation indicated in the talbe below. If estimates be

ID: 1185280 • Letter: C

Question

Consider the replacement situation indicated in the talbe below. If estimates beyond 10 years are unreliable and if the MARR is 12%, decide whether if it is expedient to replace the current equipment You are considering a project with the following financial data: Required initial investment at n = 0: $50M Project life: 10 years Estimated annual revenue: $X (unknown) Estimated annual operating cost: $15M Required minimum return 20% per year Salvage value of the project: 15% of the initial investment What is the minimum annual revenue (in $M) must be generated to make the project worthwile? X = 26.64 M X = 32.47 M X = 28.38 M X = 35.22 M

Explanation / Answer

1)no, it si not expedite replace the current equipment. 2) option c i.e X= 32.47M