Using PERT, Harold Benson was able to determine that the expectedproject complet
ID: 1235116 • Letter: U
Question
Using PERT, Harold Benson was able to determine that the expectedproject completion time for the construction of a pleasure yacht is22.5 months and the project variance is 9.
What is the probability that the project will be completed in 19months?
Round your answer to 3 decimal places; for example, .123.
What is the probability that the project will be completed in 25months?
Round your answer to 3 decimal places; for example, .123.
Using PERT, Harold Benson was able to determine that the expectedproject completion time for the construction of a pleasure yacht is22.5 months and the project variance is 9.
(a)What is the probability that the project will be completed in 19months?
Round your answer to 3 decimal places; for example, .123.
(b)What is the probability that the project will be completed in 25months?
Round your answer to 3 decimal places; for example, .123.