Complete the following statements with appropriate response. In Linear Scheduling, the Of the line indicates the production rate of the activity. The two types of overhead considered as activity indirect costs are and... A positive variance indicates that the project is ahead of schedule. Only shortening of Activities will result in a reduction of the overall project duration. Information for calculating the budgeted cost of work scheduled (BCWS) is derived is from schedule information and from the frequency of schedule updates is usually determined by the specifications, the project complexity, and____ is the most common and simplest method of assigning a cost or value to an activity, this method assumes a ...... Rate over the duration of activity. Compressing a project schedule will cause activities to become critical. Another term for BCWS is ....

Explanation / Answer

1. Slope : slope of line indicates production rate of the activity.

2. Project Overhead cost & Home office overhead cost these are the two indirect cost.

3. A positive schedule variance

4. Critical activities they are on the longest path deformation.

5. Earned value.

6. Owners request:

7. Project Budget & constant rate

8. Non critical activties.

9. Planned cost