QUESTION 10 When an owner has taken no positive action to accept or reject the c
ID: 1714595 • Letter: Q
Question
QUESTION 10 When an owner has taken no positive action to accept or reject the contractor's work in a reasonable time frame this is known as which type of acceptance? Form Implied Constructive Procrastinate QUESTION 11 The owner typically holds back a portion of each payment earned by the general contractor. Iin the construction industry, this is practice is known as retainage. O True False QUESTION 12 The difference between actual acceler ation and constuctive acceleration ithatconstructive accele ration stems from a direct order by the owner True FalseExplanation / Answer
10. It's called constructive acceptance of project.
11 yes, this type of practice known as retainage.
12. It is not visible,