13. Evaluation of a contractor\'s construction schedule should be limited to whi
ID: 1732379 • Letter: 1
Question
13. Evaluation of a contractor's construction schedule should be limited to which of the following considerations? A. B. C. Date of Completion, Date of Award, Sequence of operations Date of Award, Network Logic, Sequence of Operations Completion Date, Network Logic, Beginning Date D. Date of Award, Date of Completion, Network Logic E. Sequence of Operations, Date of Completion, Date of Completion 14. Supervision of the construction work is the responsibility of: A. the architect/engineer. B. the contractor. C. the Inspector. D. the owner. E. the Construction Management Firm 15. If a soils report for a potential construction site was prepared under a contract with the owner prior to advertising for bids, indicate which of the following may be properly included in the Contract Documents without excessive risk: 36Explanation / Answer
13. Option A is correct answer
Evaluation of contractor schedule should be limited to date of completion, date of award, sequence of operations.
Date of completion is project completion date, date of award is allocation date of project.
Sequence of operations should be checked for the progress of work
Network logic is upto the project management to do work with ease
14. Option E is correct answer
Construction management firm has to take responsibilty of supervision in construction of work.
If any hazard occurs during project project management firm is responsible for that.
15. Option B is correct answer
For potential construction site, soil report is excessively added in contract document without excessive work