A manufacturer has to meet the following shipping schedule: In the month of JANU
ID: 1944656 • Letter: A
Question
A manufacturer has to meet the following shipping schedule:
In the month of JANUARY, he is requried shipment units : 10,000
In the month of FEBRUARY, he is required shipment units: 40,000
In the month of MARCH, he is required shipment units: 20,000
Production capacity is 30,000 units and the production cost per unit is $10.
Because the company does not warehouse, storare company is utilized when needed, the bill gets determined by multiplying the number of units in storage on the last day of the month by $3.
The company start of with zero in january and would like to end with zero at the end of march.
Formulate a mathematical model to assist in minimzing the sum of the production and storage cost for the 3 month period.