The following scenario will be used for the next three questions Miser Construct
ID: 2338618 • Letter: T
Question
Explanation / Answer
Gross profit to be recognized under percentage of completion method: 2016 2017 2018 Contract price 14000000 14000000 14000000 Cost incurred till date 3000000 9000000 11800000 Estimated cost to complete 9000000 3000000 0 Total estimated costs 12000000 12000000 11800000 Estimated gross profit/(loss) 2000000 2000000 2200000 % of completion 25.00% 75.00% 100.00% Gross profit earned today 500000 1500000 2200000 Less: Gross profit earned previously 0 500000 1500000 Total Gross profit earned/recognized 500000 1000000 700000 Notes: Estimated gross profit/Loss=Contract price-Total estimated costs % of completion=Cost incurred till date/Total estimated costs The amount of profit to be recognized in 2018 is : $ 700000