In a standard cost system, variable overhead is applied Answer a. using actual d

ID: 2371574 • Letter: I

Question

In a standard cost system, variable overhead is applied Answer a. using actual direct labor hours. b. using budgeted indirect labor hours. c. using direct labor hours at practical capacity. d. using standard direct labor hours. e. all of these In a standard cost system, variable overhead is applied using actual direct labor hours. using budgeted indirect labor hours. using direct labor hours at practical capacity. using standard direct labor hours. all of these a. using actual direct labor hours. b. using budgeted indirect labor hours. c. using direct labor hours at practical capacity. d. using standard direct labor hours. e. all of these

Explanation / Answer

c.using direct labor hours at practical capacity