Problem 11-16 Measures of Internal Business Process Performance
MacIntyre Fabrications, Ltd., of Aberdeen, Scotland, has recently begun a continuous improvement campaign in conjunction with a move toward Lean Production. Management has developed new performance measures as part of this campaign. The following operating data have been gathered over the last four months:
Month
Management would like to know the company%u2019s throughput time, manufacturing cycle efficiency, and delivery cycle time. The data to compute these measures have been gathered and appear below:
Month
Compute the manufacturing cycle efficiency (MCE) for each month. (Round your answers to 1 decimal place. Omit the "%" sign in your response.)
Assume that in month 5 the move time, process time, and so forth, are the same as for month 4, except that through the implementation of Lean Production, the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE. (Round your answers to 1 decimal place. Omit the "%" sign in your response.)
Assume that in month 6 the move time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE. (Round your answers to 1 decimal place. Omit the "%" sign in your response.)
MacIntyre Fabrications, Ltd., of Aberdeen, Scotland, has recently begun a continuous improvement campaign in conjunction with a move toward Lean Production. Management has developed new performance measures as part of this campaign. The following operating data have been gathered over the last four months:
Explanation / Answer
1 2 3 4 ============================================================================================================================== Process time 0.6 0.5 0.5 0.4 ============================================================================================================================== Inspection time 0.7 0.7 0.4 0.3 ============================================================================================================================== Move time 0.5 0.5 0.4 0.5 ============================================================================================================================== Queue time 3.6 3.6 2.6 1.7 ============================================================================================================================== total 5.4 5.3 3.9 2.9 ============================================================================================================================================================================================= Manufacturing cycle ============================================================================================================================== Process tiem + through put time 11.1% 9.4% 12.8% 13.8% ============================================================================================================================== Wait tme 9.6 8.7 5.3 4.7 ============================================================================================================================== through put time 5.4 5.3 3.9 2.9 ============================================================================================================================== Total devlivery time 15 14.0 9.2 7.6 ============================================================================================================================== please rate my answer with fiev stars