Alongi Corporation uses the following activity rates from its activity-based cos
ID: 2375581 • Letter: A
Question
Alongi Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products.
How much overhead cost would be assigned to Product P91M using the company's activity-based costing system? (Do not round your intermediate calculation. Round your final answer to two decimal places.)
Activities Activity Rate Setting up batches $ 74.76 per batch Processing customer orders $ 55.40 per customer order Assembling products $ 1.36 per assembly hour
Explanation / Answer
Overhead cost = 74.76*33+55.40*1+1.36*368 = $3022.96