Cost Pool Driver & Level Cost in Pool Use of Driver by D Use of Driver by F
Equipment Setup----------500 setups----------------$1,000,000-----------------350 setups------------------150 setups
Materials Ordering--------10,000 orders-------------$2,000,000-----------------7,000 orders----------------3,000 orders
Quality Control-------------4,000 inspections--------$500,000-------------------2,000 inspections----------2,000 inspections
Machining-------------------50,000 machine hrs-----$5,000,000----------------40,000 machine hrs-------10,000 machine hrs
What is the overhead cost per unit for Product F when all overhead is applied based on machine hours?
a) $170
b) $340
c) $68
d) $200
What is the overhead cost per unit for Product D when all overhead is applied based on machine hours?
a) $170
b) $68
c) $340
d) $40
Explanation / Answer
.over heead cost per unit for" F" = over head applied / machine hoursi got for product D i.e ans: (a) $170