Performance Products Corporation makes two products, titanium Rims and Posts. Da

ID: 2378651 • Letter: P

Question


Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:



Direct


Labor-Hours Annual


per unit Production





Additional information about the company follows:


a. Rims require $24 in direct materials per unit, and Posts require $16.


b. The direct labor wage rate is $11 per hour.


c. Rims are more complex to manufacture than Posts and they require special equipment.


d. The ABC system has the following activity cost pools:




Estimated Activity







1.


Compute the activity rate for each activity cost pool. (Round your final answers to 2 decimal places.)



Activity Cost Pool Activity Rate


Machine setups ?per setup


Special processing ?per setup


General factory ?per setup


rev: 02-15-2011





2.


Determine the unit product cost of each product according to the ABC system. (Do not round intermediate calculation. Round your final answers to 2 decimal places.)




Unit product cost of Rims $


Unit product cost of Posts $


Rims 0.50 27,000 units     Posts 0.10 53,000 units

Explanation / Answer

Activity rates:
Machine setups - $15525/135 = $115 per setup
Spl Processing - $72,000/3600 = $20 per machine hour
General factory - $206,800/18800 = $11 per direct labor hour

2. Unit product costs

Cost element ----- Rims ----- Posts
Direct Materials -- $24.00----- $16.00
Direct labor (11x0.50) 5.50 ----- 2.75
Overheads
Setup @115 ---- 1150 ------690
Proeceesing @20
General @11---- 121 -----121
Total costs $1,300.50 -- $829.75