I know how this should be set up I just don\'t know what numbers I\'m calcuating
ID: 2380143 • Letter: I
Question
I know how this should be set up I just don't know what numbers I'm calcuating (basically anwhere I put ??? is what I need help with.
Bryson Company operates two factories. The company applies factory overhead to jobs on the basis of machine hours in Factory 1 and on the basis of direct labor hours in Factory 2. Estimated factory overhead costs, direct
C)
Journalizing the entries to apply factory overhead to production in each factory for November.
I know it should be set up like just don't understand what numbers to calcuate
Factory 1 work in process ???
Factory overhead ???
Factory 2 work in process ???
Factory overhead ???
d)
Determine the balances of the factory accounts for each factory as of November 30, and indicate whether the amounts represent overapplied factory overhead or underapplied factory overhead.
Factory 1 $???? Debit Underapplied
Factory 2 $???? Credit Overrapplied
Explanation / Answer
C)
Journalizing the entries to apply factory overhead to production in each factory for November.
I know it should be set up like just don't understand what numbers to calcuate
Factory 1 work in process 48048
Factory overhead 48048
Factory 2 work in process 76000
Factory overhead 76000
d)
Determine the balances of the factory accounts for each factory as of November 30, and indicate whether the amounts represent overapplied factory overhead or underapplied factory overhead.
Factory 1 $5152 Debit Underapplied
Factory 2 $3200 Credit Overrapplied