The following account appears in the ledger after only part of the postings have

ID: 2380228 • Letter: T

Question

The following account appears in the ledger after only part of the postings have been completed for July, the first month of the current fiscal year:

Work in Process
Balance, July 1
60,200

Direct materials
147,000

Direct labor
120,000



Factory overhead is applied to jobs at the rate of 60% of direct labor cost. The actual factory overhead incurred for July was $75,000. Jobs completed during the month totaled $301,200.

(a) Prepare the journal entries to record (1) the application of factory overhead to production during July and (2) the jobs completed during July.

(b) What is the balance of the factory overhead account on July 31?

(c) Was factory overhead overapplied or underapplied on July 31?

(d) Determine the cost of the unfinished jobs on July 31.

Explanation / Answer

The following account appears in the ledger after only part of the postings have been completed for July, the first month of the current fiscal year:

                   Work in Process              
Balance, July 1    53,200 |                  
Direct materials 147,000 |                  
Direct labor      120,000 |                  

Factory overhead is applied to jobs at the rate of 60% of direct labor cost. The actual factory overhead incurred for July was $75,000. Jobs completed during the month totaled $301,200
.
(a)     Prepare the journal entries to record (1) the application of factory overhead to production during July and (2) the jobs completed during July.     

(1)

Work in Process

72,000

    Factory Overhead

72,000

(2)

Finished Goods

301,200

    Work in Process

301,200


(b)     What was the balance of the factory overhead account on July 31?     

= $75,000 - $72,000

= $3,000 Debit
          
(c)     Was factory overhead overapplied or underapplied on July 31?     

Underapplied
          
(d)     Determine the cost of the unfinished jobs on July 31.

Total debits to Work in Process:

   Balance, July 1

$ 53,200

   Direct materials

147,000

   Direct labor

120,000

   Factory overhead

  72,000

$392,200

Less cost of goods finished during July

301,200

Balance, Work in Process, July 31

(cost of unfinished jobs)

$ 91,000

========

now you can do your own.

if this is not helpful you may try this link as well

http://www.cramster.com/answers-apr-09/accounting/cost-jobs-account-appears-ledger_547269.aspx?rec=0

please rate my answer if you find it helpful

(1)

Work in Process

72,000

    Factory Overhead

72,000

(2)

Finished Goods

301,200

    Work in Process

301,200