Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Pick the correct answer, show work 30. Lewis Company calculates its predetermine

ID: 2388595 • Letter: P

Question

Pick the correct answer, show work

30. Lewis Company calculates its predetermined rates using practical volume, which is 288,000 units. The standard cost system allows 2 direct labor hours per unit produced. Overhead is applied using direct labor hours. The total budgeted overhead is $3,168,000, of which $864,000 is fixed overhead. The actual results for the year are as follows:

Units produced:          280,000
Direct labor:              570,000 hours @ $9
Variable overhead:     $2,320,000
Fixed overhead:         $872,000

The predetermined fixed overhead rate is:

a. $3 per direct labor hour.
b. $1.50 per direct labor hour.
c. $5.50 per direct labor hour.
d. $4 per direct labor hour.
e. none of these.

31. The predetermined variable overhead rate is:

a. $3.00 per direct labor hour.
b. $1.50 per direct labor hour.
c. $5.50 per direct labor hour.
d. $4.00 per direct labor hour.
e. none of these.


32. Calculate the applied fixed overhead.

a. $840,000
b. $855,000
c. $864,000
d. $910,000
e. none of these

33. Calculate the fixed overhead spending variance.

a. $32,000 F
b. $0
c. $8,000 U
d. $32,000 U
e. $8,000 F




Explanation / Answer

30.Option " b" is the correct answer pre determined over head rate = Expected over head / allocation base = $864000 / 576000 hours = 1.50 [here labor hours = 288000 *2 = 576000 hours ] 31.option " d" is the correct answer. = [$3168000-$864000]/576000 = $4 32.option "C" is the correct answer here first the budgeted fixed over head would be applied , and then the mangement will decide wether it is under applied or over applied.The under /over applied cost wiil be adjusted with cost of good sold a/c. 33.option "c" is the correct answer. $864000-$872000 = $ 8000 un favourable