Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Brady Construction Company contracted to bulld an apartment complex for a price

ID: 2392091 • Letter: B

Question

Brady Construction Company contracted to bulld an apartment complex for a price of $6,500,000. Construction began In 2018 and was completed in 2020. The following is a series of Independent situations, numbered 1 through 6, Involving differing costs for the project. All costs are stated In thousands of dollars. Estimated Costs to Complete (As of the End of the Costs Incurred During Year Year) Sltuation 2018 2019 2020 2018 2019 2020 11,650 2,580 1350 3,930 1350 2 1650 1350 3,000 3,930 3,000 3 1650 2,580 2,800 3,930 2,700 4 650 3,150 1,300 4,550 950 5 650 3,150 2,350 4,550 2,700 6 650 3,150 3,300 6,055 3,050 Requlrec Complete the following table. (Do not round Intermedlete calculatlons. Enter answers In dollars. Round your final answers to the nearest whole doller. Negatlve amounts should be Indicated by a mlnus sign.) Gross Profit (Loss) Recogniz Revenue Recognized Over Time Revenue Recognized Upon Completion Situation 2018 2019 2020 2018 2019 2020 5 272,043

Explanation / Answer

Gross Profit (Loss) Recognised

Revenue Recognised Over Time

Revenue Recognised Upon completion

Situations

2018

2019

2020

2018

2019

2020

1

272043

425376

222581

0

0

(6500000 – 5280000)

=1220000

2

272043

-22043

250000

0

0

(6500000 – 6930000)

=-430000

3

272043

-534515

-267528

0

0

(6500000 – 6630000)

=-130000

4

162500

1237500

0

0

0

(6500000 – 5500000)

=1000000

5

162500

-162500

350000

0

0

(6500000 – 7250000)

=-750000

6

-19873

-174272

-405855

0

0

(6500000 – 9105000)

=-2605000

Revenue Recognised Over Time (Percentage completion Method) :-

Total gross profit = Contract Price – Total cost

Total cost = Cost incurred during the year + Estimated cost to complete

Situation 1 :-

Contract Price = 6500000

   Total cost = 1650000{cost incurred} + 3930000 {Estimated cost} = 5580000

Total Gross Profit = 6500000 – 5580000 = 920000

2018 = Gross profit recognized = Total gross profit * percentage of completion

% of completion = cost incurred/ total cost

      = 1650000/5580000 = 29.57%

      GP recognized = 920000 * 29.57% = 272043

2019 = % = (1650 + 2580)/(1650 + 2580 + 1350) = 75.81%

Total GP = 6500000 – 5580000 = 920000

   GP = 920000 * 75.81% = 697419

GP recognized = 697419 – 272043 = 425376

2020 = GP recognized = 920000 – 697419 = 222581

Situation 2 :-

Contract Price = 6500000

   Total cost = 1650000{cost incurred} + 3930000 {Estimated cost} = 5580000

Total Gross Profit = 6500000 – 5580000 = 920000

2018 = Gross profit recognized = Total gross profit * percentage of completion

% of completion = cost incurred/ total cost

      = 1650000/5580000 = 29.57%

      GP recognized = 920000 * 29.57% = 272043

2019 = % = (1650 + 1350)/(1650 + 1350 + 3000) = 50%

Total GP = 6500000 – 6000000 = 500000

   GP = 500000 * 50% = 250000

GP recognized = 250000 – 272043 = -22043

2020 = GP recognized = 500000 – 250000= 250000

Situation 3 :-

Contract Price = 6500000

   Total cost = 1650000{cost incurred} + 3930000 {Estimated cost} = 5580000

Total Gross Profit = 6500000 – 5580000 = 920000

2018 = Gross profit recognized = Total gross profit * percentage of completion

% of completion = cost incurred/ total cost

      = 1650000/5580000 = 29.57%

      GP recognized = 920000 * 29.57% = 272043

2019 = % = (1650 + 2580)/(1650 + 2580 + 2700) = 61.04%

Total GP = 6500000 – 6930000= -430000

   GP = -430000 * 61.04% = -262472

GP recognized = -262472 – 272043 = -534515

2020 = GP recognized

Total GP = 6500000 – 7030000= -530000

GP recognized = -530000 + 262472= -267528

Situation 4 :-

Contract Price = 6500000

   Total cost = 650000{cost incurred} + 4550000 {Estimated cost} = 5200000

Total Gross Profit = 6500000 – 5200000 = 1300000

2018 = Gross profit recognized = Total gross profit * percentage of completion

% of completion = cost incurred/ total cost

      = 650000/5200000 = 12.5%

      GP recognized = 1300000 * 12.5% = 162500

2019 = % = (650 + 3150)/( 650 + 3150 + 950) = 80%

Total GP = 6500000 – 4750000= 1750000

   GP = 1750000 * 80%= 1400000

GP recognized = 1400000 – 162500= 1237500

2020 = GP recognized

Total GP = 6500000 – 5100000= 1400000

GP recognized = 1400000 - 1400000= 0

Situation 5 :-

Contract Price = 6500000

   Total cost = 650000{cost incurred} + 4550000 {Estimated cost} = 5200000

Total Gross Profit = 6500000 – 5200000 = 1300000

2018 = Gross profit recognized = Total gross profit * percentage of completion

% of completion = cost incurred/ total cost

      = 650000/5200000 = 12.5%

      GP recognized = 1300000 * 12.5% = 162500

2019 = % = (650 + 3150)/( 650 + 3150 + 2700) = 58.46%

Total GP = 6500000 – 6500000= 0

GP recognized = 0 – 162500= – 162500

2020 = GP recognized

Total GP = 6500000 – 6150000= 350000

GP recognized = 350000

Situation 6 :-

Contract Price = 6500000

   Total cost = 650000{cost incurred} + 6055000 {Estimated cost} = 6705000

Total Gross Profit = 6500000 – 6705000= -205000

2018 = Gross profit recognized = Total gross profit * percentage of completion

% of completion = cost incurred/ total cost

      = 650000/6705000= 9.69%

      GP recognized = -205000* 9.69% = -19873

2019 = % = (650 + 3150)/( 650 + 3150 + 3050) = 55.47%

Total GP = 6500000 – 6850000= -350000

GP = -350000 * 55.47%= -194145

GP recognized = -194145 + 19873= – 174272

2020 = GP recognized

Total GP = 6500000 – 7100000= -600000

GP recognized = -600000 + 194145 = -405855

Gross Profit (Loss) Recognised

Revenue Recognised Over Time

Revenue Recognised Upon completion

Situations

2018

2019

2020

2018

2019

2020

1

272043

425376

222581

0

0

(6500000 – 5280000)

=1220000

2

272043

-22043

250000

0

0

(6500000 – 6930000)

=-430000

3

272043

-534515

-267528

0

0

(6500000 – 6630000)

=-130000

4

162500

1237500

0

0

0

(6500000 – 5500000)

=1000000

5

162500

-162500

350000

0

0

(6500000 – 7250000)

=-750000

6

-19873

-174272

-405855

0

0

(6500000 – 9105000)

=-2605000