Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Fogerty Company makes two products-titanium Hubs and Sprockets. Data regarding t

ID: 2412278 • Letter: F

Question

Fogerty Company makes two products-titanium Hubs and Sprockets. Data regarding the two products follow Direct Labor- Hours per Unit Productiorn 0.60 23,000 units 0.20 51,000 units Annual Hubs Sprockets Additional information about the company follows a. Hubs require $39 in direct materials per unit, and Sprockets require $17. b. The direct labor wage rate is $17 per hour. C. Hubs require special equipment and are more complex to manufacture than Sprockets d. The ABC system has the following activity cost pools Activit Estimated Overhead Cost $ 25,515 Activity Cost Pool (Activity Measure) Machine setups (number of setups) Special processing (machine-hours) General factory (organization-sustaining) Hubs Sprockets Total 243 0 3,600 NA 108 135 $162,000 3,600 NA $177,000 NA Required: 1. Compute the activity rate for each activity cost pool 2. Determine the unit product cost of each product according to the ABC system

Explanation / Answer

Answer

Total Overheads

Total Activities

Activity rate per cost driver

Machine setup cost

$       25,515.00

243

$                      105.00

per no. of setups

Special processing cost

$    1,62,000.00

3600

$                         45.00

per machine hours

General Factory cost

$    1,77,000.00

NA

NA

Working for allocation to Hubs

Activity rate per cost driver

No. of activity driver

Overhead allocated

Machine setup cost

$             105.00

per no. of setups

135

$          14,175.00

Special processing cost

$                45.00

per machine hours

3600

$      1,62,000.00

TOTAL Overhead allocated

$      1,76,175.00

No. of units

23000

Overhead cost per unit

$                    7.66

Working for allocations to Sprockets

Activity rate per cost driver

No. of activity driver

Overhead allocated

Machine setup cost

$             105.00

per no. of setups

108

$          11,340.00

Special processing cost

$                45.00

per machine hours

0

$                         -  

TOTAL Overhead allocated

$          11,340.00

No. of units

51000

Overhead cost per unit

$                    0.22

Answer----

Hubs

Sprockets

A

Direct Material

$                39.00

$                        17.00

B = labor hour per unit x $17

Direct Labor

$                10.20

$                          3.40

C = allocated above

Overhead cost per unit

$                  7.66

$                          0.22

D = A+B+C

Total Unit product cost as per ABC

$                56.86

$                        20.62

Total Overheads

Total Activities

Activity rate per cost driver

Machine setup cost

$       25,515.00

243

$                      105.00

per no. of setups

Special processing cost

$    1,62,000.00

3600

$                         45.00

per machine hours

General Factory cost

$    1,77,000.00

NA

NA