Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The following six capital projects are considered for a manufacturing company an

ID: 2426343 • Letter: T

Question


The following six capital projects are considered for a manufacturing company and the
project will end at the end of 10 years. The initial investments for the projects are 300k,
400k, 450k, 500k, and 600k. The annual return for these projects are 80k, 100k, 105k,125k and 140k and the salvage value for these projects
at the end of year 10 are 50k, 50k,60k, 75k and 75k respectively. You have 1 million dollars to fund the right projects. Use
the methods outlined in lesson 6 and create an optimum portfolio. Use a MARR of 10%

Explanation / Answer

By comparing the net present value of projects, we can decide about the project to be funded first and onwards. The project having higher NPV should be selected. Calculation of NPV when MARR = 10% (in $K) Projects Year PV Factor = 1 / (1+r)^n A B C D E Cash Flows PV Cash Flows PV Cash Flows PV Cash Flows PV Cash Flows PV 0 1 -300     -300.00 -400     -400.00 -450     -450.00 -500     -500.00 -600     -600.00 1 0.909090909 80         72.73 100         90.91 105         95.45 125      113.64 140      127.27 2 0.826446281 80         66.12 100         82.64 105         86.78 125      103.31 140      115.70 3 0.751314801 80         60.11 100         75.13 105         78.89 125         93.91 140      105.18 4 0.683013455 80         54.64 100         68.30 105         71.72 125         85.38 140         95.62 5 0.620921323 80         49.67 100         62.09 105         65.20 125         77.62 140         86.93 6 0.56447393 80         45.16 100         56.45 105         59.27 125         70.56 140         79.03 7 0.513158118 80         41.05 100         51.32 105         53.88 125         64.14 140         71.84 8 0.46650738 80         37.32 100         46.65 105         48.98 125         58.31 140         65.31 9 0.424097618 80         33.93 100         42.41 105         44.53 125         53.01 140         59.37 10 0.385543289 80         30.84 100         38.55 105         40.48 125         48.19 140         53.98 Salvage value 0.385543289 50         19.28 50         19.28 60         23.13 75         28.92 75         28.92 Net Present Value 210.84 233.73 218.31 296.99 289.16 Project D (Investment $500k) having a higher NPV i.e.$296.99 k , hence it should be selected first. Remaining investment of $500 K should be used to fund project B having higher NPV compared to project A and C as Project E not possible to start with $500K. Optimum Portfolio is as under Project D $500K Project B $400K Balance in cash $100K Total Fund $1 million