Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Cox Engineering performs cement core tests in its laboratory. The following stan

ID: 2435370 • Letter: C

Question

Cox Engineering performs cement core tests in its laboratory.

The following standards have been set for each core test performed:


Direct materials
* Standard hours/quantity 3 pounds
* Standard price/rate $0.75 per pound


Direct labor
* Standard hours/quantity 0.4 hours
* Standard price/rate $12 per hour


Variable manufacturing overhead
* Standard hours/quantity 0.4 hours
* Standard price/rate $9 per hour


During March, the laboratory performed 2,000 core tests.

On March 1 no direct materials (sand) were on hand.

Variable manufacturing overhead is assigned to core tests on the basis of direct labor hours.

The following events occurred during March:
* 8,600 pounds of sand were purchased at a cost of $7,310.
* 7,200 pounds of sand were used for core tests.
* 840 actual direct labor hours were worked at a cost of $8,610.
* Actual variable manufacturing overhead incurred was $3,200.


The materials price variance for March is:
1) $860 unfavorable.
2) $860 favorable.
3) $281 unfavorable.
4) $281 favorable.

Save

Explanation / Answer

The formula for calculating the Material price variance is

(Actual price - Standard price) * Actual quantity

According to the given information,

The actual price is obtained by dividing the (Actual cost / Actual quantity)

Actual price = $7,310 / 8600

                  = $0.85

Standard price = $0.75

Actual quantity = 8600

Substituting the values in the above formula, we get

Material price variance = ($0.85 - $0.75) * 8600

                                  = $860 favourable

Since the value is positive, the price variance is favorable.

Therefore, the correct option is 2) $860 favorable.