Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Cox Engineering performs cement core tests in its laboratory. The following stan

ID: 2435374 • Letter: C

Question

Cox Engineering performs cement core tests in its laboratory.

The following standards have been set for each core test performed:


Direct materials
* Standard hours/quantity 3 pounds
* Standard price/rate $0.75 per pound


Direct labor
* Standard hours/quantity 0.4 hours
* Standard price/rate $12 per hour


Variable manufacturing overhead
* Standard hours/quantity 0.4 hours
* Standard price/rate $9 per hour


During March, the laboratory performed 2,000 core tests.

On March 1 no direct materials (sand) were on hand.

Variable manufacturing overhead is assigned to core tests on the basis of direct labor hours.

The following events occurred during March:
* 8,600 pounds of sand were purchased at a cost of $7,310.
* 7,200 pounds of sand were used for core tests.
* 840 actual direct labor hours were worked at a cost of $8,610.
* Actual variable manufacturing overhead incurred was $3,200.


The labor rate variance for March is
1. $4,578 unfavorable
2. $1,470 UNFAVORABLE
3. $4,578 FAVORABLE
4. $1,470 FAVORABLE

Explanation / Answer

The formula for calculating the Labor rate variance is

Labor rate variance = (Actual rate - Standard rate) * Actual hours of labor used

According to the given information,

Actual rate = Actual cost / Actual labor hours

                 = $8,610 / 840

                = $10.25 per hour

Standard rate = $12 per hour

Actual hours of labor used = 840

Substituting the values in the above formula, we get

Labor rate variance = ($10.25 - $12) * 840

                             = -$1,470 (unfavorable)

Since the value is negative, the labor rate variance is unfavorable.

Therefore, the correct option is 2) $1,470 unfavorable