Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Cox Engineering performs cement core tests in its laboratory. The following stan

ID: 2435377 • Letter: C

Question

Cox Engineering performs cement core tests in its laboratory.

The following standards have been set for each core test performed:


Direct materials
* Standard hours/quantity 3 pounds
* Standard price/rate $0.75 per pound


Direct labor
* Standard hours/quantity 0.4 hours
* Standard price/rate $12 per hour


Variable manufacturing overhead
* Standard hours/quantity 0.4 hours
* Standard price/rate $9 per hour


During March, the laboratory performed 2,000 core tests.

On March 1 no direct materials (sand) were on hand.

Variable manufacturing overhead is assigned to core tests on the basis of direct labor hours.

The following events occurred during March:
* 8,600 pounds of sand were purchased at a cost of $7,310.
* 7,200 pounds of sand were used for core tests.
* 840 actual direct labor hours were worked at a cost of $8,610.
* Actual variable manufacturing overhead incurred was $3,200.


The variable overhead efficiency variance for March is
1. $320 favorable
2. $320 unfavorable
3. $360 unfavorable
4. $360 favorable

Explanation / Answer

The formula for calculating the variable overhead efficiency variance is

(Actual hours - Standard hours) * Standard variable overhead rate

According to the given information,

Actual hours = 840

Standard hours = 0.4 * 2000

                       = 800

Standard rate = $9 per hour

Substituting the values in the above formula,we get

     Variable overhead efficiency variance = (840 - 800) * $9

                                                             = $360 (favourable)

Since the value is positive, the efficiency variance is favorable.

The correct option is 4) $360 favorable.