8. Actual overhead is $700,000, while budgeted overhead is $598,000. What is the
ID: 2439339 • Letter: 8
Question
8. Actual overhead is $700,000, while budgeted overhead is $598,000. What is the fixed overhead static-budget variance if 250,000 units are produced and 225,000 are budgeted?Select one: a. $102,000 unfavourable b. $100,000 favourable c. $80,000 favourable d. $102,000 favourable 8. Actual overhead is $700,000, while budgeted overhead is $598,000. What is the fixed overhead static-budget variance if 250,000 units are produced and 225,000 are budgeted?
Select one: a. $102,000 unfavourable b. $100,000 favourable c. $80,000 favourable d. $102,000 favourable
Select one: a. $102,000 unfavourable b. $100,000 favourable c. $80,000 favourable d. $102,000 favourable
Explanation / Answer
Fixed overhead static budget variance = Actual overhead-Budgeted overhead
= 700000-598000
Fixed overhead static budget variance = 102000 U
So answer is a) $102000 Unfavorable