Marsha Blant plans to build a concrete walkway for his home during his vacation.
ID: 2442762 • Letter: M
Question
Marsha Blant plans to build a concrete walkway for his home during his vacation. The following schedule shows how projecy time will be allocated:Hours
Purchase Materials 5
Obtain rental equipment 3
Remove sod and level site 10
Build forms for concrete 12
Mix and pour concrete into forms 5
Level concrete and smooth 2
Let dry 22
Remove forms from concrete 1
Return rental tools 1
Clean up 2
a) Identify the value-added activities. How much of the total is value-added time?
b) Identify the non-value-added activities. How much total time is spent performing non-value-added activities?
c) Calculate the manufacturing cycle efficiency.