Marc Corp has a job-order costing system. The following debits(credits) appeared in the Work in Process (WIP) account for themonth of May: May01            Balance                                 $ 10,000 May31           DirectMaterial                      $  60,000 May31            Direct Labor                         $ 40,000 May31          ManufacturingOverhead         $ 32,000      May 31          To FinishedGoods                 $(120,000) Marc applies overhead to jobs at a predetermined rate of 80%of direct labor cost. Job No 23 the only job still in process atthe end of May has been charged with direct labor of $5,000. Whatis the amount of direct materials charged to Job 23? I need help to understand how to calculate the direct materialcharge can anyone provide a suggestion this is all the informationI have been provided and it is not with in a book and no example toreflect a formula or method of calculating. Please help I will giveextra rating if you can help me understand this problem aswritten. Marc Corp has a job-order costing system. The following debits(credits) appeared in the Work in Process (WIP) account for themonth of May: May01            Balance                                 $ 10,000 May31           DirectMaterial                      $  60,000 May31            Direct Labor                         $ 40,000 May31          ManufacturingOverhead         $ 32,000      May 31          To FinishedGoods                 $(120,000) Marc applies overhead to jobs at a predetermined rate of 80%of direct labor cost. Job No 23 the only job still in process atthe end of May has been charged with direct labor of $5,000. Whatis the amount of direct materials charged to Job 23? I need help to understand how to calculate the direct materialcharge can anyone provide a suggestion this is all the informationI have been provided and it is not with in a book and no example toreflect a formula or method of calculating. Please help I will giveextra rating if you can help me understand this problem aswritten.

Explanation / Answer

Work in process, ending balance:
= Beg, 10,000 + DM, 60,000 + DL, 40,000 + OH, 32,000 - FG,120,000
= End, 22,000

Direct materials charged to Job No. 23—x:
x + $5,000 + 0.8($5,000) = $22,000
x + $4,000 = $17,000
x = $13,000