Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Pinacle Corp. budgeted $262,660 of overhead cost for 2012. Actual overhead costs

ID: 2454064 • Letter: P

Question

Pinacle Corp. budgeted $262,660 of overhead cost for 2012. Actual overhead costs for the year were $262,090. Pinacle's plantwide allocation base, machine hours, was budgeted at 48,270 hours. Actual machine hours were 54,540. A total of 93,480 units was budgeted to be produced and 98,000 units were actually produced. Pinacle's plantwide factory overhead rate for 2012 is:

Round to the nearest cent. Select the correct answer.

a. $5.44 per machine hour

b. $2.81 per machine hour

c. $2.80 per machine hour

d. $5.43 per machine hour

Explanation / Answer

Budgeted overheads = $262660

Budgeted machine hours = 48270

Plantwide factory overhead rate = 262660/48270 = $5.44 per machine hour