Chasse Homes Inc. manufactures mobile homes. Chasse uses ajob order cost system.
ID: 2457712 • Letter: C
Question
Chasse Homes Inc. manufactures mobile homes. Chasse uses ajob order cost system. The time tickets from October jobs aresummarized below.
Job502 2,352
Job503 1,440
Job504 960
Job505 1,320
Factorysupervision 2,760
Factory overhead is applied to jobs on the basis of apredetermined overhead rate of $20 per direct labor hour. Thedirect labor rate is $12 per hour.
Explanation / Answer
Job 502
Total Factory laborcost = Total factory labour hours X Per labourhour Rate Total factory labourhours =Job 502
2352 503 1440 504 960 505 1320 Total labour 6072 hours Total Factory laborcost = 6072 X $12 = $72,864 Total FactoryOverhead = Factory overhead hours X Overhead rate = 2760 X $20 = $55,200 Factory Overheads transferred in toWork -in-progress and shown as expense in income statement.