Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Please show the steps to solve this problem. Accepting Business at a Special Pri

ID: 2468837 • Letter: P

Question

Please show the steps to solve this problem.

Accepting Business at a Special Price

Power Serve Company expects to operate at 82% of productive capacity during May. The total manufacturing costs for May for the production of 31,160 batteries are budgeted as follows:

The company has an opportunity to submit a bid for 3,000 batteries to be delivered by May 31 to a government agency. If the contract is obtained, it is anticipated that the additional activity will not interfere with normal production during May or increase the selling or administrative expenses.

What is the unit cost below which Power Serve Company should not go in bidding on the government contract? Round your answer to two decimal places.
$ per unit

Direct materials $425,900 Direct labor 156,600 Variable factory overhead 43,816 Fixed factory overhead 88,000 Total manufacturing costs $714,316

Explanation / Answer

As it is anticipated, If the contract is obtained,  that the additional activity will not interfere with normal production during May or increase the selling or administrative expenses, the fixed Factory overhead will remain same even if the contract of producing additional 3000 batteries.

The direct material cost per battery = $425900 / 31160 batteries = $13.67 per battery

The direct labour cost per battery = $ 156600 / 31160 batteries = $5.03 / battery

The variable factory overhead cost per unit = $43816 / 31160 batteries = $1.41 / battery.

The unit cost below which Power Serve Company should not go in bidding on the government contract

= direct material cost / unit + direct labour cost / unit + Variablbe overhead cost per unit

= $13.67 + $5.03 + $1.41 = $20.11 per unit