Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Citation Builders, Inc., builds office buildings and single-family homes. The of

ID: 2472194 • Letter: C

Question

Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture of the down payment. Occasionally, homes remain unsold for as long as three months after construction. In these situations, sales price reductions are used to promote the sale.

     During 2013, Citation began construction of an office building for Altamont Corporation. The total contract price is $20 million. Costs incurred, estimated costs to complete at year-end, billings, and cash collections for the life of the contract are as follows:

   

   

    Also during 2013, Citation began a development consisting of 12 identical homes. Citation estimated that each home will sell for $630,000, but individual sales prices are negotiated with buyers. Deposits were received for eight of the homes, three of which were completed during 2013 and paid for in full for $630,000 each by the buyers. The completed homes cost $477,000 each to construct. The construction costs incurred during 2013 for the nine uncompleted homes totaled $2,730,000.

   

The percentage-of-completion method of recognizing revenues and costs on long-term construction contracts is equivalent to recognizing revenue at the point of delivery.

     

Answer the following questions assuming that Citation uses the completed contract method for its office building contracts:

   

What is the amount of gross profit or loss to be recognized for the Altamont contract during 2013 and 2014?

           

How much revenue related to this contract will Citation report in its 2013 and 2014 income statements?

              

What will Citation report in its December 31, 2013, balance sheet related to this contract (ignore cash)?

       

Answer the following questions assuming that Citation uses the percentage-of-completion method for its office building contracts.

   

What is the amount of gross profit or loss to be recognized for the Altamont contract during 2013 and 2014?

            

How much revenue related to this contract will Citation report in its 2013 and 2014 income statements?

     

What will Citation report in its December 31, 2013, balance sheet related to this contract (ignore cash)?

       

Assume that as of year-end 2014 the estimated cost to complete the office building is $9,150,000 and that Citation uses the percentage-of-completion method.

   

What is the amount of gross profit or loss to be recognized for the Altamont contract during 2014?

     

How much revenue related to this contract will Citation report in the 2014 income statement?

          

What will Citation report in its 2014 balance sheet related to this contract (ignore cash)?

           

    

What will Citation report in its 2013 income statement and 2013 balance sheet related to the single-family home business (ignore cash in the balance sheet)?

Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture of the down payment. Occasionally, homes remain unsold for as long as three months after construction. In these situations, sales price reductions are used to promote the sale.

     During 2013, Citation began construction of an office building for Altamont Corporation. The total contract price is $20 million. Costs incurred, estimated costs to complete at year-end, billings, and cash collections for the life of the contract are as follows:

Explanation / Answer

(‘1) Under Completed contract method all revenue is recognised when project is completed.

But under Percentage of completion method recognise revenue throughout the period of contract.

Under Percentage of completion method degree of completion is determined by comparing cost already incurred with the recent estimates of total expected costs to complete the project.

Hence under percentage of completion method recording of cost and recognising revenue is not equivalent to recognising the revenue at the point of delivery i.e. completed contract method.

Answer- Statement is False.

(‘2) Completed Contract Method

(‘a) and (‘b)

Particulars

2013

2014

Gross Profit

-

-

Income

-

-

As office building contract is completed in 2015 , hence income and profit will be recognised in year 2015 only.

(‘c) Actual cost incurred will be charged to Construction In Process Account, which is an Inventory account and will be shown in asset side in balance sheet as Inventory.

Extract balance sheet as at the end of year 2013

Asset

Amount

Liabilities

Amount

Current Asset

Current Liability

Inventory

Construction in Process

4,564,000

Billing on construction in process

2,300,000

Cash

2,070,000

Accounts Receivable

(2300,000-2070,000)

230,000

(‘3) Percentage of Completion Method

(‘a)

Particular

2013

2014

2015

Contract Price (A)

20,000,000

20,000,000

20,000,000

Cost Incurred in the year (B)

4564,000

9161,000

4575,000

Cost incurred to date

(C)

4564,000

13,725,000

18,300,000

Estimated Cost to complete (D)

11,736,000

4575,000

-

Total Estimated Cost (C+D) = E

16300,000

18300,000

Total Estimated Profit

(A-E) = F

3700,000

1700,000

Percentage of Completion to date C/E = G

28 %

75 %

100 %

Total Gross Profit to be Recognised ( F x G)

1036,000

1275,000

Less; Gross Profit Recognised in Previous years

0

1036,000

Gross Profit Recognised in Current Year

1036,000

239,000

(‘b)

Particulars

2013

2014

Contract Price

20,000,000

20,000,000

Percentage of Completion

28 %

75 %

Revenue to be recognised till date

5600,000

15000,000

Revenue reported in last year

0

5600,000

Revenue recognised in current year

5600,000

9400,000

(‘C) Extract Balance Sheet as on end of 2013.

Asset

Amount

Liabilities

Amount

Current Asset

Current Liability

Inventory

Construction in Process

0

Billing on construction in process

2,300,000

Cash

2,070,000

Accounts Receivable

(2300,000-2070,000)

230,000

Construction in Process is charged to expense account construction expense while recognising revenue. Rest treatment will be same as in completed contract method.

Particulars

2013

2014

Gross Profit

-

-

Income

-

-