Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 11-9A Hopkins Clothiers is a small company that manufactures tall-men’s

ID: 2474100 • Letter: P

Question

Problem 11-9A

Hopkins Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2014, 10,600 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 14,500 direct labor hours. All materials purchased were used.

Cost Element

Standard (per unit)

Actual


Overhead is applied on the basis of direct labor hours. At normal capacity, budgeted fixed overhead costs were $53,650, and budgeted variable overhead was $36,250.

Compute the overhead controllable variance and the overhead volume variance

Your answer is partially correct. Try again.

Explanation / Answer

Overhead controllable variance => Actual Overhead - Budgeted allowance based on standard hours allowed

Budgeted allowance based on standard hours allowed =>

Variable => (10600*1.43)*2.50 => 37895

Fixed => 53650

Overhead controllable variance => (49900 + 37000) - (37895 + 53650)

=> $4645 F

Overhead Volume variance => Budgeted allowance based on standard hours allowed* – Overhead charged to production**

Budgeted allowance based on standard hours allowed* => Budgeted fixed expenses + variable expenses (standard hours allowed for actual production × variable overhead rate)

=> 53650 + (10600*1.43*2.50) => $91545

Overhead charged to production** => Standard hours allowed × Standard overhead rate

=>  Standard hours allowed * 6.20

As , Standard overhead rate not given, so volume variance can not be calculated

One more formula to calculate this varaince

Overhead Volume variance => Recovered Overhead* - Budgeted overhead

Recovered Overhead* => (Budgeted Overhead / Budgeted Units) * Actual Units

in this i need budgeted units to , which is also not given, so cant be calculate.