Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Use the following information for the next three questions. The following inform

ID: 2476390 • Letter: U

Question

Use the following information for the next three questions. The following information is available for BCo. BCo makes micro-wave ready meals. Planned production for the year was 6,000 units. 9. Prepare a flexible budget for production costs based on actual output. 10. Calculate the material variances. Label the variances, and indicate whether the variance is favorable or unfavorable. 11. Based on your answer to the previous question, identify one possible cause for each variance. Please do not say they used more or less of the input than planned. (Extra point if you can find one possible cause to explain both variances.)

Explanation / Answer

The flexible budget for production costs means the standard cost of each item mentioned below is multiplied by actual units and compared with actual cost to find out the variance

Material @ 1.1 pound per unit at $5 per pound

labor at 0.2 hours per unit or in 1 hour 5 units are produced @$12 per hour

variable overhead @1/3 oven hour per unit or 1 oven hour for production of 3 units at $9 per hour

The fixed cost is same for budget units and actual units produced

The tabular form of flexible production budget is given below

B.Co

Production Budget report (Flexible)

Variable cost per unit

flexible budget

Actual

variance

favourable / unfavourable

production units

5800

5800

Variable

direct material

5.5

31900

30800

1100

favourable

labor

2.4

13920

13800

120

favourable

variable overhead

3

17400

17400

fixed cost

8000

8000

total Production cost

71220

70000

1220

favourable

The steps to calculate the direct material price variance as are as below

Step 1 – calculate the actual cost, the formula is

Actual cost = Actual quantity * actual price

Actual cost = 5600 * 5.5

Actual cost = $30,800

Step 2 – calculate the standard cost of actual quantity, the formula is

Standard cost = Actual quantity * standard price

Standard cost = 5600 * 5.5

Standard cost = $ 30,800

To calculate the material price variance the formula is

Material price variance = Actual cost – standard cost

Variance = 30800 – 30800

Variance = 0

It is no variance as actual cost is equal to standard cost

The steps to calculate the direct material usage variance as are as below.

Step 1 – to calculate the standard cost of actual quantity for, the formula is

Standard cost of actual quantity = Actual quantity * standard price

Standard cost of actual quantity = 5600 * 5.5

Standard cost of actual quantity = $30,800

Step 2 – to calculate the standard cost of standard quantity, the formula is

Standard cost of standard quantity = Standard quantity * standard price

Standard quantity = 5800 units manufactured * 1.1pounds

Standard quantity = 6380

Standard cost of standard quantity = 6380 * 5.5

Standard cost of standard quantity = $ 35,090

To calculate the material price usage variance the formula is

Material price usage variance = Standard cost of actual quantity – Standard cost of standard quantity

Variance = 30,800 – 35,090

Variance = 4290

It is favorable variance as actual quantity used for manufacturing 5800 units is less than standard quantity required to manufacture 5800

the reason for poszitive material usage is the standard material for production of 1 unit is 1.1 pound but actual usage is 0.97 pound per unit means per meal , material used is less than budget , it can be due to less wastage or defects in production during the year

B.Co

Production Budget report (Flexible)

Variable cost per unit

flexible budget

Actual

variance

favourable / unfavourable

production units

5800

5800

Variable

direct material

5.5

31900

30800

1100

favourable

labor

2.4

13920

13800

120

favourable

variable overhead

3

17400

17400

fixed cost

8000

8000

total Production cost

71220

70000

1220

favourable