Picard Landscaping plants grass seed as the basic landscaping for business campu

ID: 2483025 • Letter: P

Question

Picard Landscaping plants grass seed as the basic landscaping for business campuses. During a recent month, the company worked on three projects (Remington, Chang, and Wyco). The company is interested in controlling the materials costs, namely the grass seed, for these plantings projects.

In order to provide management with useful cost control information, the company uses standard costs and prepares monthly variance reports. Analysis reveals that the purchasing agent mistakenly purchased poor-quality seed for the Remington project. The Chang project, however, received higher-than-standard-quality seed that was on sale. The Wyco project received standard-quality seed. However, the price had increased and a new employee was used to spread the seed.

Shown below are quantity and cost data for each project.

Actual

Standard

a) prepare a variance report for the purchasing department , b) prepare a variance report for the production department

Actual

Standard

Project Quantity Costs Quantity Costs Total Variance Remington 540 lbs. $1,296 450 lbs. $1,170 $126 U Chang 400 920 410 1,066 146 F Wyco 590 1,593 500 1,300 293 U     Total variance $273 U

Explanation / Answer

a)

Actual price = Actual costs / Actual quantity

Standard price = Standard costs / Standard quantity

Material Price Variance = Actual Quantity * (Actual Price – Standard Price)

PICARD LANDSCAPING

Variance Report – Purchasing Department

Project

Actual pounds purchased

Actual price

Standard Price

Price Variance

Explanation

Remington

540

$1,296/540 lbs.

$ 2.40

$1,170/450 lbs.

$ 2.60

540 * ($2.40 - $2.60)

$ 108.00

F

Purchased poor quality seeds

Chang

400

$920/400 lbs.

$ 2.30

$1,066/410 lbs.

$ 2.60

400 * ($2.30 - $2.60)

$ 120.00

F

Seeds on sale

Wyco

590

$1,593/590 lbs.

$ 2.70

$1,300/500 lbs.

$ 2.60

590 * ($2.70 - $2.60)

$ 59.00

U

Price increased

Total price variance

$169.00

F

b)

Material Quantity Variance = Standard Price * (Actual Quantity – Standard Quantity)

PICARD LANDSCAPING

Variance Report – Production Department

Project

Actual pounds purchased

Standard Pounds

Standard Price

Quantity Variance

Explanation

Remington

540

450

$1,170/450 lbs.

$ 2.60

$2.60 * (540-450)

$ 234.00

U

Purchased poor quality seeds

Chang

400

410

$1,066/410 lbs.

$ 2.60

$2.60 * (400-410)

$ 26.00

F

Purchased higher quality seeds

Wyco

590

500

$1,300/500 lbs.

$ 2.60

$2.60 * (590-500)

$ 234.00

U

New Employee

Total quantity variance

$ 442.00

U

PICARD LANDSCAPING

Variance Report – Purchasing Department

Project

Actual pounds purchased

Actual price

Standard Price

Price Variance

Explanation

Remington

540

$1,296/540 lbs.

$ 2.40

$1,170/450 lbs.

$ 2.60

540 * ($2.40 - $2.60)

$ 108.00

F

Purchased poor quality seeds

Chang

400

$920/400 lbs.

$ 2.30

$1,066/410 lbs.

$ 2.60

400 * ($2.30 - $2.60)

$ 120.00

F

Seeds on sale

Wyco

590

$1,593/590 lbs.

$ 2.70

$1,300/500 lbs.

$ 2.60

590 * ($2.70 - $2.60)

$ 59.00

U

Price increased

Total price variance

$169.00

F