Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Prepare entries to record the following transactions related to the construction

ID: 2490739 • Letter: P

Question

Prepare entries to record the following transactions related to the construction of a building by the Village of Silver Springs. The Village adopts a formal budget and uses encumbrance accounting.  Make all required entries for the Capital Projects Fund only.

a. The Village Council adopts a capital budget at the beginning of the year. To finance construction of the building, the Village will transfer $3,000,000 from its General Fund and apply for a state grant of $1,000,000. It appropriates $3.6 million for construction and '$400,000 for furniture and equipment.

b. The General Fund transfers $3,000,000 to the Capital Projects Fund for the new project

c. The state approves Silver Springs' application for a $1,000,000 construction grant and simultaneously sends a check to the Village.

d. Silver Springs awards a construction contract in the amount of $3,400,000.

e. The contractor sends a progress billing to Silver Springs in the amount of $1,600,000. The bill is approved by the Village engineers and a voucher is prepared, less a 10% retainage pending completion of the building and final approval by the Village. Silver Spring considers 25% of the billing to be the state's share of the cost.

f. The voucher in "e" above is paid.

g. The contractor encounters construction problems due to unforeseen soil conditions.  As a result, Silver Springs authorizes a change order for '$200,000

h. The contractor completes construction and sends Silver Springs an invoice for the remaining $2,000,000. The Village engineers inspect the building and accept the work. The invoice is approved and paid, together with the amount retained on the progress billing in "e" above. Silver Springs considers 25% of the billing to be the state's share of the cost.

Explanation / Answer

Answer:

a. Estimated other financing sources                                                               3,000,000

                        Estimated revenues                                                                 1,000,000

                              Appropriations                                                                                        4,000,000

                             

                  b.   Cash                                                                                        3,000,000

                              Transfer in from General Fund                                                               3,000,000

c. Cash 1,000,000

                              Advance on construction grant                                                              1,000,000

                  d. Encumbrances                                                                         3,400,000

                              Budgetary fund balance reserved for encumbrances                             3,400,000

                  e.   Budgetary fund balance reserved for encumbrances               1,600,000

                              Encumbrances                                                                                         1,600,000

                        Expenditures - construction costs                                            1,600,000

                              Construction contracts payable                                                              1,440,000

                              Retainage payable                                                                                      160,000

     

                        Advance on construction grant                                                   400,000

                              Revenues - construction grant                                                                   400,000

                  f.   Construction contracts payable                                                1,440,000

                              Cash                                                                                                        1,440,000

                  g.   Encumbrances                                                                             200,000

                              Budgetary fund balance reserved for encumbrances                                200,000

                 

                  h.   Budgetary fund balance reserved for encumbrances               2,000,000

                              Encumbrances                                                                                         2,000,000

                        Expenditures - construction costs                                            2,000,000

                              Construction contracts payable                                                              2,000,000

                        Construction contracts payable                                                2,000,000

                        Retainage payable                                                                       160,000

                              Cash                                                                                                        2,160,000

                        Advance on construction grant 500,000

                              Revenues - construction grant 500,000