Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The following standard costs were developed for one of the products of Rammy Cor

ID: 2508037 • Letter: T

Question

The following standard costs were developed for one of the products of Rammy Corporation: STANDARD COST CARD PER UNIT Materials: 4 feet x $14.25 per foot = $ 57.00 Direct labor: 8 hours x $10 per hour = 80.00 Variable overhead: 8 direct labor hours x $8 per hour = 64.00 Fixed overhead: 8 direct labor hours x $12 per hour = 96.00 Total standard cost per unit $297.00 The following information is available regarding the company's operations for the period: Units produced: 11,000 Materials purchased: 52,000 feet @ $13.95 per foot Materials used: 40,000 feet Direct labor: 84,000 hours costing $840,000 Manufacturing overhead incurred: Variable $756,000 Fixed $1,000,000 Budgeted fixed manufacturing overhead for the period is $960,000, and the standard fixed overhead rate is based on expected capacity of 80,000 direct labor hours. Required: (be sure to show all calculations and label each answer clearly) a. Calculate the materials price variance. b. Calculate the materials usage variance.

Explanation / Answer

Material price variance=(standard price-actual price)*actual Quantity

=(14.25-13.95)*52000

=$15600(favourable)


Material usage variance=(Standard quantity-actual quantity)*Standard price

=(4*11000-52000)*14.25

=$114000(unfavourable)



Total material variance=57*11000-52000*13.95

=$98400(unfavourable)

=Material price variance+Material usage variance