Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Beavis Construction Company was the low bidder on a construction project to buil

ID: 2513156 • Letter: B

Question

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below:

                                                                                    2012                           2013

Costs incurred during the year                               $450,000                $ 1.100,000

Estimated costs to complete 1,050,000                      0

Billings during the year                                            400,000                    1,400,000

Cash collections during the year                             300,000                     1,500,000

Assume that Beavis uses the percentage- of- completion method for revenue recognition.

Required:

Compute the amount of gross profit recognized during 2012 and 2013.

Prepare all journal entries related to the construction project in 2012 and 2013.

Prepare Statement of Financial Position end of 2012 and 2013 (if any).

(please provide the answer step by step)

Explanation / Answer

2012:

$1800000

Contract price

450000

Actual costs to date

1050000

Estimated costs to complete

1500000

Total estimated project costs

Estimated total gross profit

300000

Percentage of completion: $450,000/ $1,500,000

30%

Gross profit recognized

$90000

2013:

Contract price

$1800000

Costs incurred:

2012

$450000

2013

1100000

Total cost

1550000

Total gross profit

250000

Recognized in 2012

90000

Recognized in 2013

$160000

General journal

Debit

Credit

2012:

Construction in progress

450000

Cash

450000

Accounts receivable

400000

Billings on construction contract

400000

Cash

300000

Accounts receivable

300000

Construction in progress

90000

Cost of construction

450000

Revenue from long-term contracts

540000

2013:

Construction in progress

1100000

Cash

1100000

Accounts receivable

1400000

Billings on construction contract

1400000

Cash

1500000

Accounts receivable

1500000

Construction in progress

160000

Cost of construction

1100000

Revenue from long-term contracts

1260000

Billings on construction contract

1800000

Construction in progress

1800000

2012:

$0

2013:

Contract price

$1800000

Costs incurred:

2012:

$450000

2013:

$1100000

Total costs

$1550000

Total gross profit

$250000

2012:

$1800000

Contract price

450000

Actual costs to date

1050000

Estimated costs to complete

1500000

Total estimated project costs

Estimated total gross profit

300000

Percentage of completion: $450,000/ $1,500,000

30%

Gross profit recognized

$90000

2013:

Contract price

$1800000

Costs incurred:

2012

$450000

2013

1100000

Total cost

1550000

Total gross profit

250000

Recognized in 2012

90000

Recognized in 2013

$160000