McCallister Company uses an activity-based cost system. The following ABC rates
ID: 2514533 • Letter: M
Question
McCallister Company uses an activity-based cost system.
The following ABC rates have already been calculated.
Job 317 has the following inputs.
20 direct labor hours (the direct labor rate is $25 per hour)
30 pounds of materials (the material cost is $5 per pound)
6 setups
8 machine hours
A. Enter the total amount of overhead applied to this job.
B. Compute the total cost of the job, including overhead.
Overhead pools Activity rate Pool A............ $5 per direct labor hour Pool B............ $1000 per setup Pool C........... $2 per machine hourExplanation / Answer
A Overhead Pool A 100 =20*5 Pool B 6000 =1000*6 Pool C 16 =8*2 Total 6116 B Direct materials 150 =30*5 Direct labor 500 =20*25 Overhead 6116 Total cost of the job 6766