Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

ABC Dress Shop produces high quality formal dresses. In April 2018 they produced

ID: 2527752 • Letter: A

Question

ABC Dress Shop produces high quality formal dresses. In April 2018 they produced 16,000 dresses. For the month of April the following standard and actual cost data are available. The normal monthly capacity of the company is 40,000 direct labor hours. All material purchased in April was used in April production.

Standard per Dress

Actual

Direct materials

5.0 yards @ $8.50 per yard

$643,250 for 83,000 yards

Direct labor

2.0 hours @ $12.00 per hour

$425,000 for 34,000 hours

Overhead

hours @ $5.15 per hour

(fixed $3.25; variable $1.90)

$125,000 fixed overhead

$49,000 variable overhead

Overhead is applied on the basis of direct labor hours. At normal capacity, budgeted fixed overhead costs are $130,000 per month and budgeted variable overhead costs are $76,000 per month.

Required

a. Calculate the direct materials price variance for April. Label the variance as favorable or unfavorable.

b. Calculate the direct materials quantity variance for April. Label the variance as favorable or unfavorable.

c. Calculate the direct labor rate variance for April. Label the variance as favorable or unfavorable.

d. Calculate the direct labor efficiency variance for April. Label the variance as favorable or unfavorable.

e. Calculate the variable overhead spending variance for April. Label the variance as favorable or unfavorable.

f. Calculate the variable overhead efficiency variance for April. Label the variance as favorable or unfavorable.

g. Calculate the fixed overhead spending variance for April. Label the variance as favorable or unfavorable.

h. Calculate the fixed overhead production volume variance for April. Label the variance as favorable or unfavorable.

i. Which of the variances should be investigated if management considers a variance of more than 5% from standard to be significant?

j. Provide a discussion of the tradeoffs that might exist between the direct material and direct labor variances.

Standard per Dress

Actual

Direct materials

5.0 yards @ $8.50 per yard

$643,250 for 83,000 yards

Direct labor

2.0 hours @ $12.00 per hour

$425,000 for 34,000 hours

Overhead

hours @ $5.15 per hour

(fixed $3.25; variable $1.90)

$125,000 fixed overhead

$49,000 variable overhead

Explanation / Answer

Answers

Actual DATA for

16000

units

Quantity (AQ)

Rate (AR)

Actual Cost

Direct Material

83000 yards

$                7.75

$       6,43,250.00

Direct labor

34000 hours

$              12.50

$       4,25,000.00

Variable Overhead

34000 hours

$                1.44

$          49,000.00

Standard DATA for

16000

units

Quantity (SQ)

Rate (SR)

Standard Cost

Direct Material

80000 yards

$                8.50

$       6,80,000.00

Direct labor

32000 hours

$              12.00

$       3,84,000.00

Variable Overhead

32000 hours

$                1.90

$           60,800.00

Material Price Variance [Answer ‘a’]

(

Standard Rate

-

Actual Rate

)

x

Actual Quantity

(

$                 8.50

-

$                 7.75

)

x

83000

62250

Variance

62250

Favourable-F

Material Quantity Variance [Answer ‘b’]

(

Standard Quantity

-

Actual Quantity

)

x

Standard Rate

(

80000

-

83000

)

x

$                           8.50

-25500

Variance

25500

Unfavourable-U

Material Spending Variance

(

Standard Cost

-

Actual Cost

)

(

$   6,80,000.00

-

$   6,43,250.00

)

36750

Variance

36750

Favourable-F

Labor Rate Variance [Answer (c)]

(

Standard Rate

-

Actual Rate

)

x

Actual Labor Hours

(

$               12.00

-

$               12.50

)

x

34000

-17000

Variance

17000

Unfavourable-U

Labour Efficiency Variance [Answer (d)]

(

Standard Hours

-

Actual Hours

)

x

Standard Rate

(

32000

-

34000

)

x

$                        12.00

-24000

Variance

24000

Unfavourable-U

Labor Spending Variance

(

Standard Cost

-

Actual Cost

)

(

$   3,84,000.00

-

$   4,25,000.00

)

-41000

Variance

41000

Unfavourable-U

Variable Overhead Rate Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Labor Hours

(

$                 1.90

-

$                 1.44

)

x

34000

15600

Variance

15600

Favourable-F

Variable Overhead Efficiency Variance [Answer ‘f’]

(

Standard Hours

-

Actual Hours

)

x

Standard Rate

(

32000

-

34000

)

x

$                           1.90

-3800

Variance

3800

Unfavourable-U

Variable Overhead Spending Variance [Answer ‘e’]

(

Standard Cost

-

Actual Cost

)

(

$      60,800.00

-

$      49,000.00

)

11800

Variance

11800

Favourable-F

Actual DATA for

16000

units

Quantity (AQ)

Rate (AR)

Actual Cost

Direct Material

83000 yards

$                7.75

$       6,43,250.00

Direct labor

34000 hours

$              12.50

$       4,25,000.00

Variable Overhead

34000 hours

$                1.44

$          49,000.00

Standard DATA for

16000

units

Quantity (SQ)

Rate (SR)

Standard Cost

Direct Material

80000 yards

$                8.50

$       6,80,000.00

Direct labor

32000 hours

$              12.00

$       3,84,000.00

Variable Overhead

32000 hours

$                1.90

$           60,800.00