Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Use the following information for the Problems below. [The following information

ID: 2528424 • Letter: U

Question

Use the following information for the Problems below.

[The following information applies to the questions displayed below.]

Trico Company set the following standard unit costs for its single product.


The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter. The following flexible budget information is available.


During the current quarter, the company operated at 90% of capacity and produced 54,000 units of product; actual direct labor totaled 265,000 hours. Units produced were assigned the following standard costs.


Actual costs incurred during the current quarter follow.

Direct materials (30 Ibs. @ $4 per Ib.) $ 120.00 Direct labor (5 hrs. @ $14 per hr.) 70.00 Factory overhead—variable (5 hrs. @ $8 per hr.) 40.00 Factory overhead—fixed (5 hrs. @ $10 per hr.) 50.00 Total standard cost $ 280.00 Problem 8-5AA Expanded overhead variances LO P4 (a) Compute the variable overhead spending and efficiency variances. (Round "cost per unit" and "rate per hour" answers to 2 decimal places.) AH Actual Hours SH = Standard Hours AVR Actual Variable Rate SVR Standard Variable Rate Actual Variable OH Cost Flexible Budget Standard Cost (VOH applied)

Explanation / Answer

Solution a:

Variable overhead spending variance = Variable overhead rate variance + Variable overhead efficiency variance

= $80,000 U + $40,000 F = $40,000 U

Solution b:

Fixed overhead spending variance = Budgeted fixed overhead - Actual fixed overhead

= $2,400,000 - $2,350,000 = $50,000 F

Fixed overhead volume variance = Fixed overhead applied - Budgeted fixed overhead

= (54000 * 5* $10) - $2,400,000 = $300,000 F

Solution c:

Total overhead controllable variance = Variable overhead spending variance + Fixed overhead spending variance

= $40,000 U + $50,000 F = $10,000 F

Variable overhead Cost Variance Actual Variable OH Cost Flexible Budget Standard Cost AH* AR = AH* SR = SH * SR = 265000 $8.3019 $2,200,000.00 265000 $8.00 $2,120,000.00 270000 $8.00 $2,160,000.00 $80,000 U $40,000 F Varaible overhead rate Variance Variable overhead efficiency variance