I keep getting the first part wrong can someone explain what am doing wrong. Inf

ID: 2531154 • Letter: I

Question

I keep getting the first part wrong can someone explain what am doing wrong.

Information on four investment proposals is given below:

  

Investment Proposal

1.

Compute the project profitability index for each investment proposal. (Round your answers to 2 decimal places.)

Investment Proposal

A B C D   Investment required $ (60,000) $ (70,000) $ (40,000) $ (990,000)   Present value of cash inflows 88,000    97,300 64,200    1,318,700   Net present value $ 28,000    $ 27,300 $ 24,200    $ 328,700   Life of the project 5 years    7 years 6 years    6 years

1.

Compute the project profitability index for each investment proposal. (Round your answers to 2 decimal places.)

Check Your Work Mozilla Fireox 0 ? ezlo.mheducaliun.com/.hmlpx 700 poinls nformation en four investment proposal's is given below Investment Proposa S (E0,000) (70,000) 40,000) (880,00O) Pressernt value of a inuws 9,000 $ 28,00n 27,30024,200 S 328,700 years 97,300 4,200 318 700 Lre or the project ears yeans 6 yeers Required: 1. Compute the project pror tabiny ndex tor each investment prooosal (Round your answers to 2 decimal places. Answer is complete but not entirely correct. Proposal 1 47 1.39 1.33 Rank the praposals in terms of preferenre OBCAD ODCBA OCABD O Type here to search rP ^- 4:32 PM 4/25/2018

Explanation / Answer

Proposal Number Project Profitability Index A 0.47 =28000/60000 B 0.39 =27300/70000 C 0.61 =24200/40000 D 0.33 =328700/990000