Question

If ABC budgets $340,000 in Overhead for the year and uses direct labor costs that are budgeted at $500,000 as the cost driver; then, how much overhead would they allocate to each of the following jobs, given they use a normal costing system?

340000/500000x100= .68

68% of the labor cost

JOB 1

JOB 2

Direct Materials

$800

$2,380

Direct Labor

$3,000

$12,600

Overhead

Do I add direct materials and direct labor for each and overhead is 68% of that?

JOB 1

JOB 2

Direct Materials

$800

$2,380

Direct Labor

$3,000

$12,600

Overhead

Explanation / Answer

Overhead Rate = 340,000/500,000 x 100 = 68%

Job 1 Overhead = Direct Labor x 68% = 3,000 x 68% = $2,040

Job 2 Overhead = Direct Labor x 68% = 12,600 x 68% = $8,568