Build an Earned Value Management (EVM) model using these variables: Planned Valu
ID: 2535818 • Letter: B
Question
Build an Earned Value Management (EVM) model using these variables:
Planned Value: $45,000
i.Note for understanding, this based on time, and what we expected to use based on time. Your schedule variance is based on earned and planned.
Actual Cost: $39,500
Earned Value (how much has been spent based on planned costs) : $43,500
i.Note for understanding, this usually based on expected costs at the task level. In other words, for the tasks complete the project was expected to use this much costs. Your cost variance is based on actual and earned.
Balance at Completion: $172,000
Original Time in Months: 14
Calculate in the model:
Cost Variance
Schedule Variance
Cost Performance Index
Schedule Performance Index
Estimate at Completion
Estimated Time
Use conditional formatting to render any “bad” values red, “good” values green and “0” values yellow. Do cell by Cell.
Analyze the data and denote your evaluation of the project. Include in the evaluation comments on schedule, costs, and performance
Explanation / Answer
Amount in USD ($) Planned Value? (PV) 45000 Earned Value? (EV) 43500 Actual Cost? (AC) 39500 Budget at Completion (BAC) 172000 1. Cost Variance (CV) = EV - AC = 43500-39500 4000 As Cost Variance is positive, this means we are under budget. 2. Schedule Variance (SV) = EV - PV = 43500 - 45000 (1500) As Schedule Variance is negative, this means we are behind schedule. 3. Cost Performance Index(CPI) = EV/AC = 43500/39500 1.10 AS the CPI is greater than one, we are earning more than the amount spent. In other words, we are under budget. 4. Schedule Performance Index (SPI) = EV/PV = 43500/45000 0.97 As the SPI is less than one, this means less work has been completed than the planned work. In other words, we are behind schedule. 5. Estimate at Completion = BAC/CPI = 172000/1.10 156183.91 if the project continues to progress with CPI = 1.10 until the end, we will have to spend 156183.91 USD to complete the project.