Beavis Construction Company was the low bidder on a construction project to buil

ID: 2537572 • Letter: B

Question

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,760,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below:

Required information

Assume that Beavis recognizes revenue on this contract over time according to percentage of completion.

13.Required information

Assume that Beavis recognizes revenue on this contract over time according to percentage of completion.

Prepare all journal entries to record costs, billings, collections, and profit recognition. (If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)

14.Required information

Assume that Beavis recognizes revenue upon completion of the project.

Compute the amount of gross profit recognized during 2015 and 2016.

  


15.Required information

Assume that Beavis recognizes revenue upon completion of the project.

Prepare all journal entries to record costs, billings, collections, and profit recognition.

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,760,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below:

Explanation / Answer

ans1) the amount of gross profit recognized during 2015 and 2016.

2015

Contract price $ 1760000

Actual costs to date $ 399000

Estimated costs to complete 931000

Total estimated project costs 1330000

Estimated total gross proft 430000

Percentage oF completion:

$399000/1330000 30%

Gross proft recognized $129000

2016:

Contract price $1,760000

Costs incurred:2015 $399000

2016 1,060,000

Total cost 1,459,000

Total gross proft 301000

Recognized in 2015 129000

Recognized in 2016 $172,000

ans2) all journal entries to record costs, billings, collections, and profit recognition.

2015:

Construction in progress 399000

Cash or A/P 399000

Accounts receivable 485000

Billings on construction contract 485000

Cash 385000

Accounts receivable 385000

Construction in progress 129000

Cost of construction 399000

Revenue from long-term contracts 528000

2016:

Construction in progress 1,060,000

Cash or A/P 1,060,000

Accounts receivable 1,330,000

Billings on construction receivable 1,330,000

Cash 1430000

Account REceivables 1430000

Construction in progress 172000

Cost of construction 1060000

Revenuefrom long-term contracts 1232000

Billings on construction contract 1760000

Construction in progress 1760000

ans3) mount of gross profit recognized during 2015 and 2016.

2015:$0

2016:

Contract price 1760000

Costs incurred:

2015 399000

2016 1060000
Total cost 1459000

Total gross profit 301000

ans4) all entries to record costs, billings, collections, and profit recognition.

2015:

Construction in progress 399000

Cash or A/P 399000

Accounts receivable 485000

Billings on construction contract 485000

Cash 385000

Accounts receivable 385000

2016:

Construction in progress 1060000

Cash or A/P 1060000

Accounts receivable 1330000

Billings on construction contract 1330000

Cash 1430000

Accounts receivable 1430000

Construction in progress 301000

Cost of construction 1459000

Revenue from long-term contracts 1760000

Billings on construction contract 1760000

Construction in progress 1760000

ans1) the amount of gross profit recognized during 2015 and 2016.

2015

Contract price $ 1760000

Actual costs to date $ 399000

Estimated costs to complete 931000

Total estimated project costs 1330000

Estimated total gross proft 430000

Percentage oF completion:

$399000/1330000 30%

Gross proft recognized $129000

2016:

Contract price $1,760000

Costs incurred:2015 $399000

2016 1,060,000

Total cost 1,459,000

Total gross proft 301000

Recognized in 2015 129000

Recognized in 2016 $172,000

ans2) all journal entries to record costs, billings, collections, and profit recognition.

2015:

Construction in progress 399000

Cash or A/P 399000

Accounts receivable 485000

Billings on construction contract 485000

Cash 385000

Accounts receivable 385000

Construction in progress 129000

Cost of construction 399000

Revenue from long-term contracts 528000

2016:

Construction in progress 1,060,000

Cash or A/P 1,060,000

Accounts receivable 1,330,000

Billings on construction receivable 1,330,000

Cash 1430000

Account REceivables 1430000

Construction in progress 172000

Cost of construction 1060000

Revenuefrom long-term contracts 1232000

Billings on construction contract 1760000

Construction in progress 1760000

ans3) mount of gross profit recognized during 2015 and 2016.

2015:$0

2016:

Contract price 1760000

Costs incurred:

2015 399000

2016 1060000
Total cost 1459000

Total gross profit 301000

ans4) all entries to record costs, billings, collections, and profit recognition.

2015:

Construction in progress 399000

Cash or A/P 399000

Accounts receivable 485000

Billings on construction contract 485000

Cash 385000

Accounts receivable 385000

2016:

Construction in progress 1060000

Cash or A/P 1060000

Accounts receivable 1330000

Billings on construction contract 1330000

Cash 1430000

Accounts receivable 1430000

Construction in progress 301000

Cost of construction 1459000

Revenue from long-term contracts 1760000

Billings on construction contract 1760000

Construction in progress 1760000