Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 18-9 Sunland Construction Company has entered into a contract beginning

ID: 2551956 • Letter: P

Question

Problem 18-9 Sunland Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost S594,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $901,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date Estimated costs to complete Progress billings to date Cash collected to date s255,420 $433,620 $604,000 338,580 160,380 271,000 547,000 901,000 241,000 497,000 901,000 0- (a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period. (If answer is 0, please enter 0. Do not leave any fields blank.) Gross profit recognized in 2017 Gross profit recognized in 2018 Gross profit recognized in 2019s (b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period. (If answer is O, please enter 0. Do not leave any fields blank.) Gross profit recognized in 2017 , Gross profit recognized in 2018 , Gross profit recognized in 2019

Explanation / Answer

1.Percentage of Completion Method

                                                                   2017           2018           2019

(A) Costs incurred to date                          255420       433620       604000

Estimated future costs                                338580       160380       0

(B) Estimated total costs                            594000       594000       604000

Progress billings to date                             271000       547000       901000

Cash collected to date 241000       497000       901000

C) Est. total gross profit (901000 - B) 307000       307000       297000

(D) Percent Complete (A/B)                       43%            73%            100%

Rev. Recog. to Date (901000*D) 387430       657730       901000

Current Yr. Revenue Recognized 387430       270300       243270

Total GP Recognized to Date (C*D) 132010       224110       297000

Current Yr. Gross Profit Recognized 132010       92100 72890

Gross Profit Recognized

2017 = $ 132010

2018 = $ 92100

2019 = $ 72890

2.Completed-Contract Method

2017 = $0 - No gross profit would be recognized under completed-contract method.

2018 = $0 = No gross profit would be recognized under completed-contract method.

2019 = Gross profit = $ 2,97,000

Total Price $ 9,01,000

Total Cost ($6,04,000)

Gross Profit recognized 2019 $ 2,97,000