Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Cost of Units Transferred Out and Ending Work in Process The costs per equivalen

ID: 2553689 • Letter: C

Question

Cost of Units Transferred Out and Ending Work in Process

The costs per equivalent unit of direct materials and conversion in the Rolling Department of Oak Ridge Steel Company are $2.15 and $0.75, respectively. The equivalent units to be assigned costs are as follows:

The beginning work in process inventory on July 1 had a cost of $1,910. Determine the cost of completed and transferred-out production, the ending work in process inventory, and the total costs assigned by the Rolling Department.

Equivalent Units Direct Materials Conversion Inventory in process, July 1 0 3,300 Started and completed during July 65,000 65,000 Transferred out of Rolling (completed) 65,000 68,300 Inventory in process, July 31 5,000 2,000 Total units to be assigned costs 70,000 70,300

Explanation / Answer

Answer

Direct Materials

Conversion

Transferred out of Rolling (completed) – A

65,000 units

68,300 units

Cost per Equivalent units – B

$2.15

$0.75

Cost assigned = A x B

$139,750

$51,225

Inventory in process, July 31 - A

5,000 units

2,000 units

Cost per Equivalent units – B

$2.15

$0.75

Cost assigned = A x B

$10,750

$1,500

Working

Amount

Completed and transferred out production

[139750 + 51225]

$190,975

Inventory in Process, ending

[10750 + 1500]

$12,250

Total Cost assigned by the Rolling Department

$203,225

Direct Materials

Conversion

Transferred out of Rolling (completed) – A

65,000 units

68,300 units

Cost per Equivalent units – B

$2.15

$0.75

Cost assigned = A x B

$139,750

$51,225

Inventory in process, July 31 - A

5,000 units

2,000 units

Cost per Equivalent units – B

$2.15

$0.75

Cost assigned = A x B

$10,750

$1,500