I need help with the following managerial accounting question involving Labor ra
ID: 2578146 • Letter: I
Question
I need help with the following managerial accounting question involving Labor rate and Labor rate variance efficiency.
Exercise 11-14 The Pembina Company uses a standard costing system. In August, 5,950 actual labor hours were worked at a rate of $12.60 per hour. The standard number of hours is 4,840 and the standard wage rate is $13.50 per hour. Determine the Labor Rate and Variance Labor Efficiency Variance. (Enter all variances as a positive number.) Labor Rate Variance Labor Efficiency Variance 5355 Favorable 14985 Unfavorable SHOW LIST OF ACCOUNTS LINK TO TEXTExplanation / Answer
Labour rate variance = (Standard rate – Actual rate) x Actual hours worked
= ($13.50-$12.60)*5950
= $5,355 - Favourable
Labour efficiency variance = (Standard labour hours - Actual labour hours)*standard rate
=(4840-5950)*13.50
= -$14,985 - Unfavourable
Working in progress - Labour - Debit $65,340
(standard labour hours * standard rate)
Labour efficiency variance account - Debit $14,985
To Labour rate variance account - Credit $5,355
To Wages payable - Credit $74,970
(actual labour hours *actual rate)