Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Cold Zone Mechancial Inc. manufactures cooling units for commercial buildings. T

ID: 2579663 • Letter: C

Question

Cold Zone Mechancial Inc. manufactures cooling units for commercial buildings. The price and cost of goods sold for each unit are as follows:

1

Price per unit

$75,000.00

2

Cost of goods sold

60,000.00

3

Gross profit per unit

$15,000.00

In addition, the company incurs selling and administrative expenses of $231,880. The company wishes to assign these costs to its three major customers, Good Knowledge University, Hot Shotz Arena, and Break-a-Leg Hospital. These expenses are related to three major nonmanufacturing activities: customer service, project bidding, and engineering support. The engineering support is in the form of engineering changes that are placed by the customer to change the design of a product. The budgeted activity costs and activity bases associated with these activities are:

1

Activity

Budgeted Activity Cost

Activity Base

2

Customer service

$83,720.00

Number of service requests

3

Project bidding

61,360.00

Number of bids

4

Engineering support

86,800.00

Number of customer design changes

5

Total costs

$231,880.00

Activity-base usage and unit volume information for the three customers is as follows:

Cold Zone Mechancial Inc. manufactures cooling units for commercial buildings. The price and cost of goods sold for each unit are as follows:

1

Price per unit

$75,000.00

2

Cost of goods sold

60,000.00

3

Gross profit per unit

$15,000.00

In addition, the company incurs selling and administrative expenses of $231,880. The company wishes to assign these costs to its three major customers, Good Knowledge University, Hot Shotz Arena, and Break-a-Leg Hospital. These expenses are related to three major nonmanufacturing activities: customer service, project bidding, and engineering support. The engineering support is in the form of engineering changes that are placed by the customer to change the design of a product. The budgeted activity costs and activity bases associated with these activities are:

1

Activity

Budgeted Activity Cost

Activity Base

2

Customer service

$83,720.00

Number of service requests

3

Project bidding

61,360.00

Number of bids

4

Engineering support

86,800.00

Number of customer design changes

5

Total costs

$231,880.00

Activity-base usage and unit volume information for the three customers is as follows:

X

Labels and Amount Descriptions

X

Activity rates

Shaded cells have feedback.

1. Determine the activity rates for each of the three nonmanufacturing activity pools.

Score: 30/30

1

per serv. req.

2

per bid

3

per design change

Points:

6 / 6

Feedback

Check My Work

Calculate for each activity:

Total activity cost ÷ Total activity base = Activity Rate

X

Activity Costs

Shaded cells have feedback.

2. Determine the activity costs allocated to the three customers, using the activity rates in (1).

Score: 30/30

1

Activity Costs

2

3

4

Points:

6 / 6

Feedback

Check My Work

Calculate for each customer:

Activity usage x Activity rate from Req. (1) = Activity cost; Sum all activity costs per customer to determine a total and divide the total overhead by budgeted units to derive the activity costs per unit for each customer.

X

Customer Profitability Report

Shaded cells have feedback.

3. Construct customer profitability reports for the three customers, dated for the year ended December 31, using the activity costs in (2). The reports should disclose the gross profit and income from operations associated with each customer. Refer to the lists of Labels and Amount Descriptions for the exact wording of the answer choices for text entries. Be sure to complete the statement heading. “Less”, “Plus” or colons (:) will automatically appear if required. Enter all amounts as positive numbers, except for a negative income from operations.

Score: 67/137

Cold Zone Mechanical Inc.

Customer Profitability Report

1

Good Knowledge University

Hot Shotz Arena

Break-a-Leg Hospital

2

3

4

5

6

7

8

9

10

Points:

16.63 / 34

Feedback

1

Price per unit

$75,000.00

2

Cost of goods sold

60,000.00

3

Gross profit per unit

$15,000.00

Explanation / Answer

1

The activity rates for each of the three nonmanufacturing activity pools

S.No

Activity

Activity Rate

1

Customer service

$ 260 per service request

2

Project bidding

$ 590 per bid

3

Engineering support

$ 400 per customer design change

Activity

Budgeted Activity Cost

Activity Base

Activity Rate = Budgeted Activity Cost/Activity base

Customer service

$                                         83,720

Number of service requests - 322

$                              260

Project bidding

$                                         61,360

Number of bids - 104

$                              590

Engineering support

$                                         86,800

Number of customer design changes - 217

$                              400

2

The activity costs allocated to the three customers, using the activity rates in (1)

Customer

Activity Cost

Number of Units

Cost per Unit

Good KnowledgeUniversity

                54,840

                             22

                2,493

Hot Shotz Arena

                36,140

                             14

                2,581

Break-a-Leg Hospital

             140,900

                                6

             23,483

( in $)

Good KnowledgeUniversity

Hot Shotz Arena

Break-a-Leg Hospital

Activity Usage

Acivity rate

Activity Cost

Activity Usage

Acivity rate

Activity Cost

Activity Usage

Acivity rate

Activity Cost

Customer service

                        60

                           260

             15,600

                        52

                260

            13,520

                      210

                260

            54,600

Project bidding

                        36

                           590

             21,240

                        18

                590

            10,620

                        50

                590

            29,500

Engineering support

                        45

                           400

             18,000

                        30

                400

            12,000

                      142

                400

            56,800

Total

             54,840

            36,140

          140,900

3

Construct customer profitability reports for the three customers, dated for the year ended December 31, using the activity costs in (2)

Good KnowledgeUniversity

Hot Shotz Arena

Break-a-Leg Hospital

Total

Sales units

22

14

6

42

Sales value

$                                   1,650,000

$          1,050,000

$                        450,000

$          3,150,000

Less: Cost of goods sold

$                                 (1,320,000)

$            (840,000)

$                     (360,000)

$       (2,520,000)

Gross profit

$                                       330,000

$              210,000

$                          90,000

$             630,000

Less : Overheads

$                         -  

Customer service

$                                       (15,600)

$              (13,520)

$                        (54,600)

$             (83,720)

Project bidding

$                                       (21,240)

$              (10,620)

$                        (29,500)

$             (61,360)

Engineering support

$                                       (18,000)

$              (12,000)

$                        (56,800)

$             (86,800)

Income from Operations

$                                       275,160

$              173,860

$                        (50,900)

$             398,120

1

The activity rates for each of the three nonmanufacturing activity pools

S.No

Activity

Activity Rate

1

Customer service

$ 260 per service request

2

Project bidding

$ 590 per bid

3

Engineering support

$ 400 per customer design change

Activity

Budgeted Activity Cost

Activity Base

Activity Rate = Budgeted Activity Cost/Activity base

Customer service

$                                         83,720

Number of service requests - 322

$                              260

Project bidding

$                                         61,360

Number of bids - 104

$                              590

Engineering support

$                                         86,800

Number of customer design changes - 217

$                              400