Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 18-2 Activity-Based Costing Printware Products, Inc. produces printers f

ID: 2580539 • Letter: P

Question

Problem 18-2 Activity-Based Costing Printware Products, Inc. produces printers for wholesale distributors. It has just completed packaging an order from Hawes Company for 450 printers. Before the order is shipped, the controller wants to compare the unit costs computed under the company's new activity-based costing system with the unit costs computed under its traditional costing system. Printware's traditional costing system assigned overhead costs at a rate of 240 percent of direct labor cost. Data for the Hawes order are as follows: direct materials, $17,552; purchased parts, $14,856; direct labor hours, 140; and average direct labor pay rate per hour, $17 Data for activity-based costing related to processing direct materials and purchased parts for the Hawes order follow Activity Engineering systems design Engineering hours Setup Parts production Product assembly Packaging Building occupancy Required If required, round the per unit answers to the nearest cent. 1. Use the traditional costing approach to compute the total cost and the product unit cost of the Hawes order Total cost Product unit cost Cost Driver Number of setups Machine hours Assembly hours Number of packages 5.60 per package Machine hours Activity Cost Rate $ 28 per engineering hour $ 36 per setup $ 37 per machine hour s 42 per assembly hour Activity Usage 18 engineering hours 12 setups 82 machine hours 96 assembly hours 150 packages 82 machine hours s 10 per machine hour

Explanation / Answer

ABC METHOD

$

$

DIRECT MATERIALS

17552

PURCHASED MATERIALS

14856

DIRECT LABOUR

140 Hrs

X$17

2380

ACTIVITY COSTS

9662

TOTAL

44450

COST PER PRINTER

44450/450

$98.78

TRADITIONAL METHOD

$

$

DIRECT MATERIALS

17552

PURCHASED MATERIALS

14856

DIRECT LABOUR

140 hrs

X$17

2380

ASSIGNED OVERHEAD COSTS

$2380

@240%

5712

TOTAL

40500

COST PER PRINTER

$40500/450

$90

ACTIVITY BASED

ACTIVITY COST RATE

$

ACTIVITY

COST DRIVER

$

ACTIVITY COST

PARTS PRODUCTION

37

82 hrs

3034

PROC ASSEMBLY

42

96 hrs

4032

PACKAGING

5.6

150 packages

840

SETUP

36

12 set ups

432

ENGINEERING

28

18 eng hrs

504

BUILDING OCCUPANCY

10

82 machine hrs

820

total

$9662

ABC METHOD

$

$

DIRECT MATERIALS

17552

PURCHASED MATERIALS

14856

DIRECT LABOUR

140 Hrs

X$17

2380

ACTIVITY COSTS

9662

TOTAL

44450

COST PER PRINTER

44450/450

$98.78