Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 18-3 Activity Cost Rates Tailgator Company produces four versions of its

ID: 2580542 • Letter: P

Question

Problem 18-3 Activity Cost Rates Tailgator Company produces four versions of its model 17-21 bicycle seat. The four versions have different shapes, but their processing operations and production costs are identical. During July, the following costs were incurred Direct materials Leather Metal frame Bolts $25,430 39,180 3,010 Materials handling Labor Equipment depreciation Electrical power Maintenance 8,232 4,410 2,460 5,184 Assembly Direct labor 13,230 Engineering design: Labor Electrical power Engineering overhead 4,116 1,176 7,644 Overhead Equipment depreciation Indirect labor Supervision Operating supplies Electrical power Repairs and maintenance Building occupancy overhead 7,056 30,870 17,640 4,410 10,584 21,168 52,920 July's output totaled 29,400 units. Each unit requires three machine hours of effort. Materials handling costs are allocated to the products based on direct materials cost, engineering design costs are allocated based on units produced, and overhead is allocated based on machine hours. Assembly costs are allocated based on direct labor hours, which are estimated at 882 for July During July, Tailgator Company completed 520 bicycle seats for Job 14. The activity usage for Job 14 was as follows: direct materials, $1,150; direct labor hours, 15

Explanation / Answer

Tailgator Company

Material handling costs are allocated to products based on direct material cost.

Direct material cost –

Leather            $25,430

Metal frame    $39,180

Bolts               $3,010

Total DM cost $67,620

Material handling costs –

Labor                                      $8,232

Equipment depreciation         $4,410

Electrical power                     $2,460

Maintenance                           $5,184

Total material handling cost $20,286

Proportion of Material handling cost to direct material cost = (20,286/67,620) x 100 = 30%

Assembly cost rate is allocated based on direct labor hours – 882 hours

Assembly cost = $13,230

Assembly cost rate = 13,230/882 = $15 per direct labor hour

Engineering design cost is allocated based on units produced.

Number of units produced = 29,400

Engineering design costs –

Labor                         $4,116

Electrical power         $1,176

Engineering overhead $7,644

Total engineering design cost = $12,936

Engineering design cost per unit produced = 12,936/29,400 = $0.44 per unit

Overhead cost is allocated based on machine hours.

Machine hours = 3 hours per unit

Total machine hours for 29,400 units = 29,400 x 3 = 88,200 machine hours

Overhead cost –

Equipment depreciation                     $7,056

Indirect labor                                      $30,870

Supervision                                         $17,640

Operating supplies                             $4,410

Electrical power                                 $10,584

Repairs and maintenance                   $21,168

Building occupancy overhead                        $52,920

Total overhead cost                            $144,648

Overhead cost per machine hour = $144,648/88,200 = $1.64 per machine hour

Bill of Activities - Job 14

Activity

Activity cost rate

Cost Driver Level

Activity Cost

Unit Level

Materials Handling

30%

per dollar of direct materials

$1,150

direct materials

$345

Assembly

$15

per direct labor hour

15

direct labor hours

$225

Batch Level

NONE

Product Level

Engineering Design

$0.44

per unit

520

units

$228.80

Facility Level

Overhead

$1.64

per machine hour

1,560

machine hours

$2,558.40

Total activity costs assigned to job

$3,357.20

Total units of job

520

Activity cost per unit

$6.46

Cost Summary:

Cost Summary:

Direct materials

$1,150

Activity costs

$3,357.20

Total cost of order

$4,507.20

product unit cost

$8.67

Bill of Activities - Job 14

Activity

Activity cost rate

Cost Driver Level

Activity Cost

Unit Level

Materials Handling

30%

per dollar of direct materials

$1,150

direct materials

$345

Assembly

$15

per direct labor hour

15

direct labor hours

$225

Batch Level

NONE

Product Level

Engineering Design

$0.44

per unit

520

units

$228.80

Facility Level

Overhead

$1.64

per machine hour

1,560

machine hours

$2,558.40

Total activity costs assigned to job

$3,357.20

Total units of job

520

Activity cost per unit

$6.46