Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 11-41 Overhead Calculations; Variance Interpretation (LO 11-5) Maxwell C

ID: 2589399 • Letter: P

Question

Problem 11-41 Overhead Calculations; Variance Interpretation (LO 11-5) Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $8.60 Standard fixed-overhead rate per hour: $13.80 Planned activity during the period: 33,000 machine hours Actual production: 19,200 finished units Machine-hour standard: Two completed units per machine hour Actual variable overhead: $278,050 Actual total overhead: $747,050 Actual machine hours worked: 33,500 Required: 1. Calculate the budgeted fixed overhead for the year. 2. Compute the variable-overhead spending variance. 3. Calculate the company's fixed-overhead volume variance. 4-a. Did Maxwell spend more or less than anticipated for fixed overhead? How much? 4-b. What was the difference in actual and anticipated overhead? 5. Was variable overhead underapplied or overapplied during the year? By how much? Complete this question by entering your answers in the tabs below. Required 1Required 2 Required 3 Required 4A Required 4B Required 5 Calculate the budgeted fixed overhead for the year. Budgeted fixed overhead

Explanation / Answer

Solution:

1) Budgeted Fixed Overhead for the year = Standard fixed overhead rate per hour x Planned Activity

= $13.80 x 33,000 machine hours

= $455,400

2) Variable Overhead Spending Variance

Variable Overhead Spending/Rate Variance

Actual Hourly Variable Overhead Rate

(278,050 / 33,500 actual mhs)

8.30

Per MH

Standard Hourly Variable Overhead Rate (SV)

8.60

Per MH

Variance or Difference in Rate

0.30

Per MH

x Actual Machine Hours

33500

Machine Hours

Variable Overhead Rate/Spending Variance

$10,050

Favorable

3) Fixed Overhead Volume Variance

Fixed Overhead Volume Variance

Absorbed Fixed Overheads (A) (Actual MHs worked 33,500 x Standard fixed overhead rate per hour $13.80)

$462,300

Budgeted Fixed Overheads (B) (as calculated in part 1)

$455,400

Fixed Overhead Volume Variance (A-B)

$6,900

Favorable

4-a)

Actual Fixed Overhead = Total Overhead – Total Variable Overhead = 747,050 – 278,050 = $469,000

Budgeted Fixed Overheads = $455,400

The company spend more than anticipated by $13,600

4-b)

Standard Overhead

Actual Overhead

Difference

Variable overhead

$288,100

(33,500 MHs x $8.60 standard variable overhead rate per mh

278050

Fixed Overhead

$455,400

(As calculated in part 1)

$469,000

(as calculated in part 4a)

Total Overhead

$743,500

$747,050

$3,550

The difference between actual and anticipated overhead is $3,550

5)

Applied Variable Overhead = 33,500 Actual Machine hours x $$8.60 standard variable overhead rate per mh = $288,100

Actual Variable Overhead Incurred = $278,050

Applied Overheads are higher than actual overheads, it means the Variable Overheads are Over Applied.

Over Applied Variable Overhead = $288,100 - $278,050 = $10,050

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you

Variable Overhead Spending/Rate Variance

Actual Hourly Variable Overhead Rate

(278,050 / 33,500 actual mhs)

8.30

Per MH

Standard Hourly Variable Overhead Rate (SV)

8.60

Per MH

Variance or Difference in Rate

0.30

Per MH

x Actual Machine Hours

33500

Machine Hours

Variable Overhead Rate/Spending Variance

$10,050

Favorable