Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Platoon Company is performing a post-audit of a project that was estimated to co

ID: 2589473 • Letter: P

Question

Platoon Company is performing a post-audit of a project that was estimated to cost $420,000, have a useful life of 6 years with a zero salvage value, and result in net cash inflows of $100,000 per year. After the investment was in operation for a year, revised figures indicate that it actually cost $470,000, will have a 9-year useful life, and will produce net cash inflows of $77,000. The present value of an annuity of 1 for 6 years at 10% is 4.355 and for 9 years is 5.759.

Calculate the net present value based on the actual amounts.


Determine whether the project should have been accepted.

Platoon Company is performing a post-audit of a project that was estimated to cost $420,000, have a useful life of 6 years with a zero salvage value, and result in net cash inflows of $100,000 per year. After the investment was in operation for a year, revised figures indicate that it actually cost $470,000, will have a 9-year useful life, and will produce net cash inflows of $77,000. The present value of an annuity of 1 for 6 years at 10% is 4.355 and for 9 years is 5.759.

Calculate the net present value based on the actual amounts.

Net present value =


Determine whether the project should have been accepted.

Explanation / Answer

Answer: NPV based on actual amounts:

Actual cost of the project : $470000

useful life : 9 years

Net cash inflow per year : $77000

Present value of the actual cash inflows : 77000*5.759 = $443443

Acual investment : $470000

NPV : -$26557

Based on the actual amounts NPV project should not be accepted. As it is coming out to be negative.